   Weekly progress report as on 04.05.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 19.04.12 Balance  work up to 19.04.12 Cumulative delay in Qty up to 19.04.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 4 2 0 1 0 1 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 5 1 0 0 0 0 1   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0   P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 1 0 1 1   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 7 2 0 2 0 2 2 "      " P1, P2, P3, P4, A1,P5,P6
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   P15, P14, A2, P13, P12, P11, P10
14 PIER  CAP Vytila side(Approach portion) 9 5 4 1 1 0 0 1   P1, P2, P3, A1,P4
15 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11
16 GIRDERVytila side(Approach portion) 9 2 7 0 0 0 0 0   P1 P2,  A1P1
17 DECK SLAB Palarivattom side(Approach portion) 7 6 1 0 1 0 1 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11
18 DECK SLABVytila side(Approach portion) 9 1 8 0 0 0 0 1   P1P2
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL 351 351 0 0 0 0 0 0    
20 RE WALL PCC Palarivattom 95 87 8 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.

 

 

  Date 27.04.12 28.04.12 29.04.12 30.04.12 01.05.12 02.05.12 03.05.12  
  Day Fri Sat Sun Mon Tue Wed Thurs  
  Climate sunny  sunny  sunny  rainy after 8.30pm sunny  sunny   rainy after 5.00pm  
  No.of labours 55 60.5 23 57 29 48 59  
  Remarks     no piling Sunday          
                   
  Availability of Material                 
                   
  Materials Required for week ending on 10.05.12 Available as on 04.05.12            
  Fine aggregate(M3) Ready Mix Concrete            
  Coarse aggregate(M3)            
  Cement(BAG)            
  Steel(TONN) 8 50            
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   
                   
 
Back
 
    
GIRDER P2 P3

    
    
DECK P1P2

    
    
CABLES CLEARED AT RP1 LOCATION

      
 

 

 

 

 

 

 

 