   Weekly progress report as on 27.04.2012
    

 

 

Sl No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

27

Completed

 

 

2

PILE PADANNA SIDE

24

24

Completed

 

Piling works completed.

3

PILE CAP CHERUVATHOOR SIDE

9

9

Completed

 

 

4

PILE CAP  PADANNA SIDE

8

8

Completed

 

 

5

PIER CHERUVATHOOR SIDE

9

9

Completed

 

 

6

PIER PADANNA SIDE

8

8

Completed

 

 

7

PIER CAP CHERUVATHOOR SIDE

9

8

1

1

1

1

0

0

 

P8 Pier cap complete

8

PIER CAP PADANNA SIDE

8

8

Completed

 

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

50%

50%

20%

20.00%

10.00%

20.00%

20.00%

 

RE Panel two layers complete,RC Wall 70% complete.

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

5.00%

0.00%

5.00%

5.00%

 

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

5

4

0

0

0

0

0.5

 

staging for P12-P11 girder in progress.

12

BEAM/SLAB PADANNA SIDE

8

5

3

2

0.5

0.5

0

0.5

 

P4-P5 girder complete

13

EXPANSION JOINT CHERUVATHUR SIDE

9

0

9

0

0

0

0

3

 

 

14

EXPANSION JOINT PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

15

KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

10.00%

 

 

16

KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

17

HANDRAIL CHERUVATHUR SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

Handrail horizontal casting IP

18

HANDRAIL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

17

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

 
Back
 
    
P8 PIER CAP CONCRETE

    
    
P12-P11 GIRDER STAGING IP

    
    
P12-P11 GIRDER STAGING IP

    
    
RC WALL WORK IP AT CHR SIDE

    
 
 
 

 

 

 

 

 

 

 