Description
|
Progress
|
Remarks
|
Pile concreting
|
In progress
|
Done 88 nos
|
Pile cap concreting
|
In progress
|
Done 25 nos
|
Pier concreting
|
In progress
|
Done 24 nos
|
Piercap concreting
|
In progress
|
Done 21 nos
|
Girder&Deck Slab
|
In progress
|
Done 14 nos girder& 13 deck
|
Site level survey
|
completed
|
|
shuttering work between P5-P6-for deck slab is in progress
|
In progress
|
staging work between P27-AP3 started
|
Pile load test
|
completed
|
|
7 day Cube test
|
In progress
|
28th day Cube test
|
In progress
|
BSNL, KWA site inspection for utility shifting
|
In progress
|
KSEB site inspection for utility shifting
|
In progress
|
2 post shifted in thamarassery side
|
KSEB utilities estimate
|
1st part Completed
|
DD received from RBDCK, handed over to KSEB
|
site clearing in thamarassery area
|
completed
|
|
filling work towards thamarassery side
|
In progress
|
100 % complete
|
site clearing towards NH side
|
In progress
|
filling 100% completed
|
filling work in piling location
|
Completed
|
upto AP2 area
|