ROB at Bakel
|
PROGRESS OF ROB WORK AS ON 11.09.2010 |
|
Description |
Completed/ Progress |
Remarks |
|
Span on Kasargod side |
|
|
|
Hand rail casting |
Completed |
Slow progress due to heavy rains |
|
Span on Kannur Side |
|
|
|
Concreting of 2 nos beams |
Completed |
|
|
Shuttering work for 1 no beam |
Progress |
Road Blocked on 24.07.2010 |
|