IV |
ROB at Parappanangady |
|
|
|
Pier cap (Total no of pier Cap- 21) |
Completed |
21 NOS COMPLETED |
|
RE Wall panel casting ( total600 nos) |
Completed |
|
|
Slab calicut side (total 10 nos ) |
In progress |
9nos done (adjacent span pending ) |
|
slab NH side ( 11 nos) |
In progress |
10nos done (adjacent span pending ) |
|
Retaining wall NH side |
completed |
Done LHS 100%, RHS- 100% |
|
Retaining wallcalicut side |
completed |
completed |
|
Dirt wall AP2 concreting |
completed |
Done 100% |
|
Dirt wall AP1 concreting |
completed |
Done 100% |
|
Handrail casting |
completed |
1400 nos completed. |
|
Handrail fixing |
In progress |
NH side 10 slab completed.Approach portion in progress. |
|
Handrail fixing |
In progress |
CALICUT side 9 span over.Approach portion completed. |
|
Pilling work RLY PORTION |
Completed |
PILING COMPLETED |
|
Pile cap RP1 |
Completed |
pier work in progress. |
|
Pile cap RP3 |
Completed |
Completed |
|
Pile cap RP2 |
In progress |
RFT IN PROGRESS |
|
NH side RE panel erection |
completed |
100% completed. |
|
RE wall work calicut side. |
completed |
100% completed. |
|
expansion joint |
completed |
completed. |
|
painting-slab |
In progress |
90% completed. |