Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888385
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 27.04.2012
    
IV ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side completed Done LHS 100%, RHS- 100%
  Retaining wallcalicut side completed  completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Handrail fixing In progress NH side 10 slab completed.Approach portion in progress.
  Handrail fixing In progress CALICUT side 9  span over.Approach portion completed.
  Pilling work RLY PORTION Completed PILING COMPLETED
  Pile cap RP1 Completed pier work in progress.
  Pile cap RP3 Completed Completed
  Pile cap RP2 In progress RFT IN PROGRESS
  NH side RE panel erection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab In progress 90% completed.
 
Back
 
    
RP-1 2ND LIFT CONCRETING.

    
    
RP2 PCC .

    
    
MATERIAL SHIFTING FROM LOADTEST AREA.

      
 

 

 

 

 

 

 

 

Untitled Document