Prevoius Weekly Reports

   Weekly progress report as on 20.04.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto 12.4.12 Balance  work up to 12.4.12 Cumulative delay in Qty up to 12.4.12 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER/SLAB  Pettah side(Approach portion) 4   4          
9 GIRDER/SLAB Anayara side(Approach portion) 4 0.5 3.5     0.5   0.5
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 88 12          
13 RT Wall Anayara side(Approach portion) % 100 88 12                
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 287 113          
16 RE Wall Panel Erection Pettah side(Approach portion) 400              
17 RE Wall Panel Erection Anayara side(Approach portion) 400 148 252     74    
 