   Weekly progress report as on 20.04.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 0       - -
4 PierCap 21 12 9 - 2 - 2 3
5 Deck Slab 21 1 20 - 1 1   1
6 RC wall - Kuttipuram side 120.2 - 120.2 - 5% 3% 2% 3%
                   
Date 14.04.12 16.04.12 17.04.12 18.04.12 19.04.12 20.04.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 57 57 57 57 57 57      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 54 m3 20m3              
Coarse Aggregate 108 m3 50 m3              
Cement 940 bags 340              
Steel 25MT 25MT              
                   
 
Back
 
    
SPAN P18-P19

    
    
RC WALL RAFT CONCRETING

    
    
PIER CAP P4

    
    
DECK SLAB P16-P17

    
 
 
 

 

 

 

 

 

 

 