   Weekly progress report as on 21.04.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaining for completion as per the weekly plan

Remarks

1

PILE Muthambi side

27

21

6

0

3

3

0

3

 

 

2

PILE Thamarassery side

33

32

1

0

1

0

1

1

 

 

3

PILE NH SIDE

30

30

0

0

0

0

0

0

 

 

4

PILE CAP Muthambi SIDE

9

6

3

0

0

0

0

1

 

 

5

PILE CAP Thamarassery SIDE

11

10

1

0

0

0

0

0

 

Work in progress.

6

PILE CAP NH SIDE

10

9

1

0

0

0

0

0

 

 

7

PIER Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

8

PIER Thamarassery SIDE

11

10

1

0

0

0

0

0

 

Work in progress.

9

PIER NH SIDE

10

8

2

0

0

0

0

1

 

 

10

PIER CAP Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

11

PIER CAP Thamarassery SIDE

11

8

3

0

1

0

1

1

 

 

12

PIER CAP NH SIDE

10

7

3

0

0

0

0

0

 

 

13

RE/R WALL Muthambi side

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

14

RE/R WALL Thamarassery side SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

Site clearance started

 

15

RE/R WALL NH SIDE

100%

10%

100%

0

25.00%

25.00%

0

25.00%

Raft COMPLETED.Shuttering work in progress

 

16

BEAM/SLAB Muthambi SIDE

8

5

3

0

0

0

0

0

 

 

17

BEAM/SLAB Thamarassery SIDE

10

2

8

0

0

0

0

1

 

 

18

BEAM/SLAB NH SIDE

11

4

7

0

1

1

0

1

 

 

19

HR/FP/KERB Muthambi SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

20

HR/FP/KERB thamarassery SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

21

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

23

Utility shifting

 

 

 

 

 

 

0

 

 

KSEB utility shifting started. Shifted 1 post 

 

 
Back
 
    
STEEL WORK IN PROGRESS P20-P21

    
    
STAGING IN PROGRESS P20-P21

    
    
PILING AT P17

      
 

 

 

 

 

 

 

 