   Weekly progress report as on 20.04.2012
    

 

Si No  Activity Description  Total Quantity Cumulative progress upto 19.04.12 Balance  work up to 19.04.12 Cumulative delay in Qty up to 19.04.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 4 2 0 1 1 0 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 5 1 0 0 0 0 1   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0   P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 1 0 1 1   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 7 2 0 2 0 2 2 "      " P1, P2, P3, P4, A1,P5,P6
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   P15, P14, A2, P13, P12, P11, P10
14 PIER  CAP Vytila side(Approach portion) 9 4 5 1 1 0 1 1   P1, P2, P3, A1
15 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11
16 GIRDERVytila side(Approach portion) 9 1 8 0 0 0 0 0   P1 P2
17 DECK SLAB Palarivattom side(Approach portion) 7 6 1 0 1 0 1 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11
18 DECK SLABVytila side(Approach portion) 9 0 9 0 0 0 0 1    
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL 351 351 0 0 0 0 0 0    
20

RE WALL PCC Palarivattom

 

95 87 8 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12.

 

 

  Labour Report                    
                       
  Date 13.04.12 14.04.12 15.04.12 16.04.12 17.04.12 18.04.12 19.04.12      
  Day Fri Sat Sun Mon Tue Wed Thurs      
  Climate sunny  sunny  sunny  sunny  sunny  sunny   sunny       
  No.of labours 51 16 17 42 47 47 43      
  Remarks holiday   no piling Sunday              
                       
  Availability of Material                     
                       
  Materials Required for week ending on 26.04.12 Available as on 20.04.12                
  Fine aggregate(M3) Ready Mix Concrete                
  Coarse aggregate(M3)                
  Cement(BAG)                
  Steel(TONN) 10 60                
                       
                       
                       
 
Back
 
    
RE WALL PCC

    
    
PEDESTAL CONCRETING P3

    
    
GIRDER A1P1 SHEATHING PIPE

      
 

 

 

 

 

 

 

 