Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8052907
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 13.04.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed   Piling works completed.
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 8 1 1 0 0 0 1    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/R WALL CHERUVATHOOR  SIDE 100% 40% 60% 10% 20.00% 5.00% 25.00% 20.00%   RE Panel two layers complete,RC Wall raft complete at RHS,first lift shuttering IP
10 RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 5.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 4.5 4.5 0 0.5 0.5 0 0    P11-P10 deck slab complete
12 BEAM/SLAB PADANNA SIDE 8 4.5 3.5 2 0.5 0 0.5 0.5   Reinf for P4-P5 girder complete,reinf for P6-P7 slab IP
13 HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Handrail horizontal casting IP
14 HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 04-06-2012 04-07-2012 04-08-2012 04-09-2012 04-10-2012 04-11-2012 04-12-2012      
  No of labours 78 79 60 73 61 72 72      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 750 950                
  Steel(MT) 12 20              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work to be started immediately at padanna side approach portion.            
  KSEB in progress works in progress            
  KWA currently can be managed at site                   
  Others                    
                       
                       
  AREAS OF  CONCERN AND CORRECTIVE ACTION:                
                       
1 Traffic block in effect from 22-03-12.P12-P11 deck slab to be completed by 6th April 2012.    
  Action:P10-P11 deck slab complete on 12-04-12.                
                       
2 Large amount of cables at chr side approach delays the work .Cable shifting IP.      
                       
       
 
Back
 
    
P11-P10 GIRDER CONC

    
    
P8 PIER CAP REINF IP

    
    
HANDRAIL HORIZONTAL CASTING

      
 

 

 

 

 

 

 

 

Untitled Document