Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
Piling works completed. |
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
8 |
1 |
1 |
0 |
0 |
0 |
1 |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/R WALL CHERUVATHOOR SIDE |
100% |
40% |
60% |
10% |
20.00% |
5.00% |
25.00% |
20.00% |
|
RE Panel two layers complete,RC Wall raft complete at RHS,first lift shuttering IP |
10 |
RE/R WALL PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
5.00% |
|
|
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
4.5 |
4.5 |
0 |
0.5 |
0.5 |
0 |
0 |
|
P11-P10 deck slab complete |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
4.5 |
3.5 |
2 |
0.5 |
0 |
0.5 |
0.5 |
|
Reinf for P4-P5 girder complete,reinf for P6-P7 slab IP |
13 |
HR/FP/KERB CHERUVATHOOR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
Handrail horizontal casting IP |
14 |
HR/FP/KERB PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
04-06-2012 |
04-07-2012 |
04-08-2012 |
04-09-2012 |
04-10-2012 |
04-11-2012 |
04-12-2012 |
|
|
|
|
No of labours |
78 |
79 |
60 |
73 |
61 |
72 |
72 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
750 |
950 |
|
|
|
|
|
|
|
|
|
Steel(MT) |
12 |
20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
work to be started immediately at padanna side approach portion. |
|
|
|
|
|
|
|
KSEB |
in progress |
works in progress |
|
|
|
|
|
|
|
KWA |
currently can be managed at site |
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AREAS OF CONCERN AND CORRECTIVE ACTION: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
Traffic block in effect from 22-03-12.P12-P11 deck slab to be completed by 6th April 2012. |
|
|
|
Action:P10-P11 deck slab complete on 12-04-12. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
Large amount of cables at chr side approach delays the work .Cable shifting IP. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|