   Weekly progress report as on 13.04.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 20 7 0 4 1 3 3    
2 PILE Thamarassery side 33 32 1 0 1 0 1 1    
3 PILE NH SIDE 30 30 0 0 0 0 0 0    
4 PILE CAP Muthambi SIDE 9 6 3 0 0 0 0 0    
5 PILE CAP Thamarassery SIDE 11 10 1 0 0 0 0 0   Work in progress.
6 PILE CAP NH SIDE 10 9 1 0 0 0 0 0    
7 PIER Muthambi  SIDE 9 6 3 0 0 0 0 0    
8 PIER Thamarassery SIDE 11 10 1 0 0 0 0 0   Work in progress.
9 PIER NH SIDE 10 8 2 0 0 0 0 1    
10 PIER CAP Muthambi  SIDE 9 6 3 0 0 0 0 0    
11 PIER CAP Thamarassery SIDE 11 8 3 0 1 0 1 1    
12 PIER CAP NH SIDE 10 7 3 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
15 RE/R WALL NH SIDE 100% 10% 100% 0 0.00% 0.00% 0 25.00% PCC COMPLETED.Steel work in progress  
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 2 8 0 0 0 0 1    
18 BEAM/SLAB NH SIDE 11 4 7 0 1 1 0 1    
19 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date 04-07-2012 04-08-2012 04-09-2012 04-10-2012 04-11-2012 05-12-2012 13/4/2012      
  Nof labours 45 42 65 68 72 72 70      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 75 100                
  Fine Aggreagate(m3) 75 100                
  Cement(bag) 1200 1500                
  Steel(MT) 50 100                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
                       
                       
 