Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886663
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 13.04.2012
    

MULAMKUNNATHUKAVU ROB

WEEKLY  PROGRESS REPORT TILL APRIL 13TH 2012

WORK

STATUS

BALANCE

SHORNUR SIDE

HANDRAIL FIXING COMPLTED

NIL

EXPANSION JOINT

AP1 COMPLETED

NIL

APPROACH PORTION

APPROACH SLAB CONCRETING  COMPLETED.,METALLING COMPLETED.ROAD TARRING WORK COMPLETED .FOOTPATH SLAB CONCRETING COMPLETED 100%

NIL

 

METALLING

ALL LAYERS OF WBM(3 LAYERS) COMPLETED

NIL

MASTIC ASPHALT

WORK COMPLETED

NIL

PAINTING

PAINTING UNDER TWO SPANS COMPLETED.HANDRAILS PAINTING COMPLETED AT AP1-P1,P1-P2,PAINTING OF RCC WALL PORTION COMPLETED,INNER KERB PAINTING WILL BE COMPLETED TODAY

NIL

 

M.C SIDE

RCC WALL PORTION CONCRETE COMPLETED

NIL

OUTER KERB

COMPLETED 85 METRE AT RCC WALL end(100%)

0% remaining

DRAINAGE SPOUT

COMPLETED  at M.C side,SHORNUR SIDE

Complete in 11 spans,

APPROACH SLAB,INNER KERB

APPROACH SLAB CONCRETE COMPLETED,

INNER KERB CONCRETING COMPLETED FOR 70 METRES,INNER KERB CONCRETING COMPLETED.

NIL

HANDRAIL  POST FIXING

HANDRAIL POST FIXING COMPLETED 100%)

 NIL

 FOOTPATH SLAB

CASTING 100% COMPLETED AT RE WALL PORTION.FOOTPATH SLAB CONCRETING TO BE COMPLETED

 NIL

MASTIC ASPHALT

COMPLETED

NIL

PAINTING WORKS

13 SLABS (under deck slab)COMPLETED.10 locations (pier and pier cap 11 locations)  HANDRAIL POSTS PAINTING COMPLETED IN M.C SIDE     

NIL

 

METALLING

 

 

COMPLETED 100%

NIL

RAODWORK(TARRING)

WORK COMPLETED

NIL

                            ALL MAJOR WORKS COMPLETED

                           

CUMULATIVE BALANCE WORK AT SITE

1.    Demobilisation  of machinery,cleaning of site.

 

 

MACHINERY AT SITE

1.Concrete mixer machine.(4 bag mixer)

                     2.Concrete mixer machine(1 bag mixer)

                     

                    LABOUR REPORT OF MULAMKUNNATHUKAVU ROB TILL       APRIL 13th 2012

 

DATE

HELPER

MASON

PAINTING

TOTAL

07-04-2012

5

2

2

9

08-04-2012

5

3

2

10

09-04-2012

5

3

2

10

10-04-2012

4

3

2

9

11-04-2012

5

3

2

9

12-04-2012

5

3

2

10

13-4-2012

5

2

2

9

 

 

 

 

 

 

 

 

 

 

 

 

 
Back
 
    

    
    

    
    

      
 

 

 

 

 

 

 

 

Untitled Document