MULAMKUNNATHUKAVU ROB
WEEKLY PROGRESS REPORT TILL APRIL 13TH 2012
WORK
|
STATUS
|
BALANCE
|
SHORNUR SIDE
|
HANDRAIL FIXING COMPLTED
|
NIL
|
EXPANSION JOINT
|
AP1 COMPLETED
|
NIL
|
APPROACH PORTION
|
APPROACH SLAB CONCRETING COMPLETED.,METALLING COMPLETED.ROAD TARRING WORK COMPLETED .FOOTPATH SLAB CONCRETING COMPLETED 100%
|
NIL
|
METALLING
|
ALL LAYERS OF WBM(3 LAYERS) COMPLETED
|
NIL
|
MASTIC ASPHALT
|
WORK COMPLETED
|
NIL
|
PAINTING
|
PAINTING UNDER TWO SPANS COMPLETED.HANDRAILS PAINTING COMPLETED AT AP1-P1,P1-P2,PAINTING OF RCC WALL PORTION COMPLETED,INNER KERB PAINTING WILL BE COMPLETED TODAY
|
NIL
|
M.C SIDE
|
RCC WALL PORTION CONCRETE COMPLETED
|
NIL
|
OUTER KERB
|
COMPLETED 85 METRE AT RCC WALL end(100%)
|
0% remaining
|
DRAINAGE SPOUT
|
COMPLETED at M.C side,SHORNUR SIDE
|
Complete in 11 spans,
|
APPROACH SLAB,INNER KERB
|
APPROACH SLAB CONCRETE COMPLETED,
INNER KERB CONCRETING COMPLETED FOR 70 METRES,INNER KERB CONCRETING COMPLETED.
|
NIL
|
HANDRAIL POST FIXING
|
HANDRAIL POST FIXING COMPLETED 100%)
|
NIL
|
FOOTPATH SLAB
|
CASTING 100% COMPLETED AT RE WALL PORTION.FOOTPATH SLAB CONCRETING TO BE COMPLETED
|
NIL
|
MASTIC ASPHALT
|
COMPLETED
|
NIL
|
PAINTING WORKS
|
13 SLABS (under deck slab)COMPLETED.10 locations (pier and pier cap 11 locations) HANDRAIL POSTS PAINTING COMPLETED IN M.C SIDE
|
NIL
|
METALLING
|
COMPLETED 100%
|
NIL
|
RAODWORK(TARRING)
|
WORK COMPLETED
|
NIL
|
ALL MAJOR WORKS COMPLETED
CUMULATIVE BALANCE WORK AT SITE
1. Demobilisation of machinery,cleaning of site.
MACHINERY AT SITE
1.Concrete mixer machine.(4 bag mixer)
2.Concrete mixer machine(1 bag mixer)
LABOUR REPORT OF MULAMKUNNATHUKAVU ROB TILL APRIL 13th 2012
DATE
|
HELPER
|
MASON
|
PAINTING
|
TOTAL
|
07-04-2012
|
5
|
2
|
2
|
9
|
08-04-2012
|
5
|
3
|
2
|
10
|
09-04-2012
|
5
|
3
|
2
|
10
|
10-04-2012
|
4
|
3
|
2
|
9
|
11-04-2012
|
5
|
3
|
2
|
9
|
12-04-2012
|
5
|
3
|
2
|
10
|
13-4-2012
|
5
|
2
|
2
|
9
|
|
|
|
|
|
|
|
|
|
|
|