Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887052
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 06.04.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaining for completion as per the weekly plan

Remarks

1

PILE Muthambi side

27

20

7

0

4

0

4

4

 

 

2

PILE Thamarassery side

33

32

1

0

1

0

1

1

 

 

3

PILE NH SIDE

30

30

0

0

0

0

0

0

 

 

4

PILE CAP Muthambi SIDE

9

6

3

0

0

0

0

0

 

 

5

PILE CAP Thamarassery SIDE

11

10

1

0

0

0

0

0

 

Work in progress.

6

PILE CAP NH SIDE

10

9

1

0

0

0

0

0

 

 

7

PIER Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

8

PIER Thamarassery SIDE

11

10

1

0

0

0

0

0

 

Work in progress.

9

PIER NH SIDE

10

8

2

0

1

0

1

0

 

 

10

PIER CAP Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

11

PIER CAP Thamarassery SIDE

11

8

3

0

2

0

2

1

 

 

12

PIER CAP NH SIDE

10

7

3

0

0

0

0

0

 

 

13

RE/R WALL Muthambi side

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

14

RE/R WALL Thamarassery side SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

15

RE/R WALL NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

PCC COMPLETED

 

16

BEAM/SLAB Muthambi SIDE

8

5

3

0

0

0

0

0

 

 

17

BEAM/SLAB Thamarassery SIDE

10

2

8

0

0

0

0

0

 

 

18

BEAM/SLAB NH SIDE

11

4

7

0

1

0

1

1

 

 

19

HR/FP/KERB Muthambi SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

20

HR/FP/KERB thamarassery SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

21

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

23

Utility shifting

 

 

 

 

 

 

0

 

 

KSEB utility shifting started. Shifted 1 post 

 

 
Back
 
    
PCC FOR RETAINING WALL NH SIDE

    
    
STEEL WORK IN PROGRESS P2-P3

      
 

 

 

 

 

 

 

 

Untitled Document