   Weekly progress report as on 06.04.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 20 1   1 - 1 1
4 PierCap 21 11 10 - 1 1 - 2
5 Deck Slab 21 1 20 - 1 - 1 1
                   
Date 31.04.12 02.04.12 03.04.12 04.04.12 05.04.12 06.04.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 22 49 49 49 49 49      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 38 m3 20m3              
Coarse Aggregate 76 m3 50 m3              
Cement 680 bags 150 Bags              
Steel 35MT 20 MT              
                   
                   
 
Back
 
    
SPAN P16-P17

    
    
SLAB P18-P19

    
    
PIER CAP P2

    
    
DECK SLAB P18-P19

    
 
 
 

 

 

 

 

 

 

 