Prevoius Weekly Reports

   Weekly progress report as on 06.04.2012
    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side completed Done LHS 100%, RHS- 100%
  Retaining wallcalicut side completed  completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Handrail fixing In progress NH side 10 slab completed.
  Handrail fixing In progress CALICUT side 9  span over.
  Boring at RP4 & RP1 Completed PILING COMPLETED
  Boring at RP3 Completed PILING COMPLETED
  Boring at RP2 In progress PILING COMPLETED
  Pile cap RP1 Completed pier work in progress.
  Pile cap RP3 Completed Completed
  NH side RE panel erection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab In progress 90% completed.
 
Back
 
    
RLY PORTION WORK IN PROGRESS.

    
    
HANDRAIL FIXING AP2 SIDE.

    
    
APPROACH PORTION CALICUT SIDE.

      
 

 

 

 

 

 

 

 