   Weekly progress report as on 06.04.2012
    
Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
PILE CHERUVATHOOR  SIDE 27 27 Completed    
PILE PADANNA SIDE 24 24 Completed   Piling works completed.
PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
PILE CAP  PADANNA SIDE 8 8 Completed    
PIER CHERUVATHOOR SIDE 9 9 Completed    
PIER PADANNA SIDE 8 8 Completed    
PIER CAP CHERUVATHOOR SIDE 9 8 1 1 0 0 0 0    
PIER CAP PADANNA SIDE 8 8 Completed    
RE/R WALL CHERUVATHOOR  SIDE 100% 40% 60% 10% 20.00% 10.00% 20.00% 20.00%   RE Panel two layers complete,RC Wall raft complete at RHS
RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
BEAM/SLAB CHERUVATHOOR  SIDE 9 4 5 0 1 0.5 0.5 0.5    P11-P10 girder complete
BEAM/SLAB PADANNA SIDE 8 4.5 3.5 2 0.5 0 0.5 0.5    
HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Handrail horizontal casting started
HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 
Back
 
    
REINF IP FOR P4-P5 GIRDER

    
    
P10-P11 GIRDER

    
    
DIRT WALL FIRST LIFT COMPLETE AT AP2

      
 

 

 

 

 

 

 

 