WORK
|
STATUS
|
BALANCE
|
SHORNUR SIDE
|
HANDRAIL FIXING COMPLTED
|
NIL
|
EXPANSION JOINT
|
AP1 COMPLETED
|
NIL
|
APPROACH PORTION
|
APPROACH SLAB CONCRETING COMPLETED.,METALLING COMPLETED.ROAD TARRING WORK COMPLETED .FOOTPATH SLAB CONCRETING COMPLETED 75%
|
,FOOTPATH SLAB CONCRETING PLANNED THIS WEEK.
|
METALLING
|
ALL LAYERS OF WBM(3 LAYERS) COMPLETED TH
|
NIL
|
MASTIC ASPHALT
|
WORK COMPLETED
|
NIL
|
PAINTING
|
PAINTING UNDER TWO SPANS COMPLETED.HANDRAILS PAINTING COMPLETED AT AP1-P1,P1-P2,PAINTING OF RCC WALL PORTION COMPLETED
|
NIL
|
M.C SIDE
|
RCC WALL PORTION CONCRETE COMPLETED
|
NIL
|
OUTER KERB
|
COMPLETED 85 METRE AT RCC WALL end(100%)
|
0% remaining
|
DRAINAGE SPOUT
|
COMPLETED at M.C side,SHORNUR SIDE
|
Complete in 11 spans,
|
APPROACH SLAB,INNER KERB
|
APPROACH SLAB CONCRETE COMPLETED,
INNER KERB CONCRETING COMPLETED FOR 70 METRES,INNER KERB CONCRETING COMPLETED.
|
NIL
|
HANDRAIL POST FIXING
|
HANDRAIL POST FIXING COMPLETED 100%)
|
NIL
|
FOOTPATH SLAB
|
CASTING 100% COMPLETED AT RE WALL PORTION.FOOTPATH SLAB CONCRETING TO BE COMPLETED TODAY IN M.C SIDE
|
NIL
|
MASTIC ASPHALT
|
COMPLETED
|
NIL
|
PAINTING WORKS
|
13 SLABS (under deck slab)COMPLETED.10 locations (pier and pier cap 11 locations) HANDRAIL POSTS PAINTING COMPLETED IN M.C SIDE
|
BALANCE LOCATION RCC wall,RE wall balance
|
METALLING
|
COMPLETED 100%
|
NIL
|
RAODWORK(TARRING)
|
WORK COMPLETED
|
NIL
|
CUMULATIVE BALANCE WORK AT SITE
1.painting in approach portion(only RE wall,RCC wall portion,inner kerb)
2.footpath slab at RCC wall portion at shornur side(40%)
|