   Weekly progress report as on 06.04.2012
    

WORK

STATUS

BALANCE

SHORNUR SIDE

HANDRAIL FIXING COMPLTED

NIL

EXPANSION JOINT

AP1 COMPLETED

NIL

APPROACH PORTION

APPROACH SLAB CONCRETING  COMPLETED.,METALLING COMPLETED.ROAD TARRING WORK COMPLETED .FOOTPATH SLAB CONCRETING COMPLETED 75%

,FOOTPATH SLAB CONCRETING PLANNED THIS WEEK.

 

METALLING

ALL LAYERS OF WBM(3 LAYERS) COMPLETED TH

NIL

MASTIC ASPHALT

WORK COMPLETED

NIL

PAINTING

PAINTING UNDER TWO SPANS COMPLETED.HANDRAILS PAINTING COMPLETED AT AP1-P1,P1-P2,PAINTING OF RCC WALL PORTION COMPLETED

NIL

 

M.C SIDE

RCC WALL PORTION CONCRETE COMPLETED

NIL

OUTER KERB

COMPLETED 85 METRE AT RCC WALL end(100%)

0% remaining

DRAINAGE SPOUT

COMPLETED  at M.C side,SHORNUR SIDE

Complete in 11 spans,

APPROACH SLAB,INNER KERB

APPROACH SLAB CONCRETE COMPLETED,

INNER KERB CONCRETING COMPLETED FOR 70 METRES,INNER KERB CONCRETING COMPLETED.

NIL

HANDRAIL  POST FIXING

HANDRAIL POST FIXING COMPLETED 100%)

 NIL

 FOOTPATH SLAB

CASTING 100% COMPLETED AT RE WALL PORTION.FOOTPATH SLAB CONCRETING TO BE COMPLETED TODAY IN M.C SIDE

 NIL

MASTIC ASPHALT

COMPLETED

NIL

PAINTING WORKS

13 SLABS (under deck slab)COMPLETED.10 locations (pier and pier cap 11 locations)  HANDRAIL POSTS PAINTING COMPLETED IN M.C SIDE     

BALANCE LOCATION  RCC wall,RE wall balance

 

METALLING

 

 

COMPLETED 100%

NIL

RAODWORK(TARRING)

WORK COMPLETED

NIL

                     

CUMULATIVE BALANCE WORK AT SITE

1.painting in approach portion(only RE wall,RCC wall portion,inner kerb)

2.footpath slab at RCC wall portion at shornur side(40%) 

 