Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886772
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 30.03.2012
    

WORK

STATUS

BALANCE

SHORNUR SIDE

HANDRAIL FIXING COMPLTED

NIL

EXPANSION JOINT

AP1 COMPLETED

NIL

APPROACH PORTION

APPROACH SLAB CONCRETING  COMPLETED.,METALLING COMPLETED.ROAD TARRING WORK COMPLETED .FOOTPATH SLAB CONCRETING IN PROGRESS.

,FOOTPATH SLAB CONCRETING PLANNED THIS WEEK.

 

METALLING

ALL LAYERS OF WBM(3 LAYERS) COMPLETED TH

NIL

MASTIC ASPHALT

WORK COMPLETED

NIL

PAINTING

PAINTING UNDER TWO SPANS COMPLETED.HANDRAILS PAINTING COMPLETED AT AP1-P1,P1-P2

RCC RETAINING WALL,HANDRAIL IN APPROACH PORTION

 

M.C SIDE

RCC WALL PORTION CONCRETE COMPLETED

NIL

OUTER KERB

COMPLETED 85 METRE AT RCC WALL end(100%)

0% remaining

DRAINAGE SPOUT

COMPLETED  at M.C side,SHORNUR SIDE

Complete in 11 spans,

APPROACH SLAB,INNER KERB

APPROACH SLAB CONCRETE COMPLETED,

INNER KERB CONCRETING COMPLETED FOR 70 METRES,INNER KERB PCC COMPLETED.

 .BALANCE WORK  REMAINING 80 metres.inner kerb concreting planned for next week.

HANDRAIL  POST FIXING

HANDRAIL POST FIXING COMPLETED 100%)

 NIL

PRECAST FOOTPATH SLAB

CASTING 100% COMPLETED AT RE WALL PORTION

 BALANCE WORK IN RCC WALL

MASTIC ASPHALT

COMPLETED IN 3 SPANS OUT OF 11

8 SPANS BALANCE

PAINTING WORKS

13 SLABS (under deck slab)COMPLETED.10 locations (pier and pier cap 11 locations)  RCC WALL PAINTING AND HANDRAILS IN PROGRESS                 

BALANCE LOCATION.outer kerb,handrails, and RCC wall,RE wall balance

 

METALLING

 

 

COMPLETED 100%

NIL

RAODWORK(TARRING)

WORK COMPLETED THIS WEEK

 

     

                       

CUMULATIVE BALANCE WORK AT SITE

1.Painting in approach portion

2.Footpath slab at RCC wall portion 

 
Back
 
    

    
    

    
    

      
 

 

 

 

 

 

 

 

Untitled Document