   Weekly progress report as on 30.03.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 18 3 3 3 2 1 1
4 PierCap 21 9 12 - 2 2 - 1
5 Deck Slab 21 0 21 - 1 1 - 1
                   
Date 24.03.12 26.03.12 27.03.12 28.03.12 29.03.12 30.03.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 22 22 22 22 22 22      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 35 m3 20m3              
Coarse Aggregate 70 m3 20 m3              
Cement 628 bags 150 Bags              
Steel 15 MT 15 MT              
 
Back
 
    
PIER CAP P1

    
    
GIRDER P18-P19

    
    
DECK SLAB P17-P18 CONCRETING

      
 

 

 

 

 

 

 

 