Prevoius Weekly Reports

   Weekly progress report as on 30.03.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks   
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0      
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0      
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0      
4 PILE CAP  THIRURSIDE 6 6 0 5 0 0 5 0      
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0      
6 PIER THIRUR SIDE 6 6 0 1 0 0 1 0      
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0      
8 PIER CAP THIRUR SIDE 6 4 0 3 0 0 3 0      
9 RE/R WALL CALICUT   SIDE 100% 40.00% 60% 0 10.00% 15.00% 0.00% 10.00%      
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
11 BEAM CALICUT   SIDE 12 4 8 0 1 1 3 1      
12 SLAB CALICUT SIDE 12 1 11   1 1 0 0      
13 BEAM THIRUR SIDE 6 0 6 0 0 0 0 0      
14 SLAB TIRUR SIDE                      
15 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
16 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
18 Deck Slab               1      
17 Utility shifting                      
                         
                         
                         
  Availbility of Men                     
  Date 24-02-2012 25-02-2012 26-02-2012 27-02-2012 28-02-2012 29-02-2012 30-02-2012        
  Nof labours 38 38 38 38 38 38 38        
                         
  Material Stocking Status Required Available Remarks                
  Coarse Aggreagate (m3)       RMC              
  Fine Aggreagate(m3)                      
  Cement(bag)                      
  Steel(MT)   14                  
                         
                         
  Utility shifting                      
  Utilities to be shifted Status Remarks                  
  BSNL shifting completed                    
  KSEB shifting in progress                    
  KWA shifting completed                    
  Others                      
                         
 
Back
 
    
RETAINING WALL CALICUT SIDE (2)

    
    
P8-P9 GIRDER SHUTTERING

    
    
P7-P8 DECK SLAB REINFORCEMENT

      
 

 

 

 

 

 

 

 