   Weekly progress report as on 30.03.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 29.03.12 Balance  work up to 29.03.12 Cumulative delay in Qty up to 29.03.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 2 4 0 1 1 0 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 4 2 0 1 0 1 2   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned. Piling resumed on 29.02.12
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 8 1 0 1 1 0 1   P1,  P2, P4, P3, A1, P5,P6, P7
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 7 2 0 2 1 1 2 "      " P1, P2, P3, P4, A1,P5
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   P15, P14, A2, P13, P12, P11, P10
14 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11
15 DECK SLAB Palarivattom side(Approach portion) 7 5 2 0 1 0 1 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
17 PIER CAP  Vytilla side(Approach portion) 9 4 5 0 0 0 0 1   P1,P2 , A1,P3
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
19 RE WALL PANEL 351 351 0 0 0 0 0 0    
20 RE WALL PCC Palarivattom 95 45 50 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12.

 

 

  Labour Report              
                 
  Date 23.03.12 24.03.12 25.03.12 26.03.12 27.03.12 28.03.12 29.03.12
  Day Fri Sat Sun Mon Tue Wed Thurs
  Climate sunny  sunny  sunny  sunny  sunny  sunny   sunny 
  No.of labours 87 82 19 52 67 70 72
  Remarks bar benders brought from other site no piling Sunday Bar benders brought from another site did not come
                 
  Availability of Material               
                 
  Materials Required for week ending on 05.04.12 Available as on 30.03.12          
  Fine aggregate(M3) Ready Mix Concrete          
  Coarse aggregate(M3)          
  Cement(BAG)          
  Steel(TONN) 10 50          
 
Back
 
    
PILE CONCRETING RP2 P2

    
    
PIER CONCRETING P6

    
    
BEARING PLACING A1 P1

      
 

 

 

 

 

 

 

 