   Weekly progress report as on 30.03.2012
    

PROGRESS REPORT (upto March 30th    2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 60%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

1.Column erection using tower crane for foundation work

2.PCC for RE wall 75% completed.

3.Deshuttering of trestle beam,trestle column completed

 

 

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

24-03-2012

10

26-3-2012

8

27-3-2012

10

28-3-2012

11

29-3-2012

8

30-3-2012

11

31-03-2012

10

 

 

 

 
Back
 
    
TOWER CRANE FOR COLUMN ERECTION

    
    
PCC FOR RE WALL PORTION

    
    
CRANE FOR COLUMN ERECTION AT RAILWAY PORTION

      
 

 

 

 

 

 

 

 