   Weekly progress report as on 23.03.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed   Piling works completed.
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 7 1 1 1 0 1 1    
5 PIER CHERUVATHOOR SIDE 9 9 Completed   P10,P9,P8 Piers complete
6 PIER PADANNA SIDE 8 7 1 1 1 0 1 1    
7 PIER CAP CHERUVATHOOR SIDE 9 6 3 1 0 0 1 1    
8 PIER CAP PADANNA SIDE 8 6 2 0 1 1 0 0    
9 RE/R WALL CHERUVATHOOR  SIDE 100% 20% 80% 10% 10.00% 10.00% 0.00% 20.00%   RE panel 230 nos casting complete,Retaining wall second lift complete at LHS
10 RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 4 5 0 0 0 0 0    
12 BEAM/SLAB PADANNA SIDE 8 2 6 2 2 2 0 0.5    
13 HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 
Back
 
    
REINF FORP3-P4 DECK SLAB

    
    
P11 PIER CAP STAGING

    
    
P7 PIER CAP

    
    
P3-P4 DECK SLAB REINF IP

    
 
 
 

 

 

 

 

 

 

 