Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
|
|
|
Completed |
|
|
|
2 |
PILE M.C SIDE |
36 |
36 |
|
|
|
Completed |
|
|
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
6 |
PIER M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
9 |
RCC WALL SHORNUR SIDE |
100% |
92% |
8% |
0 |
8.00% |
4.00% |
63.00% |
4.00% |
0 |
APPROACH SLAB CONCRETING completed.Metalling works COMPLETED .Precast slabs concreting completed .Painting works in progress.Inner kerb concreting completed this week .Mastic asphalt work completed this week in shornur side |
10 |
RE/R WALL M.C SIDE |
100% |
95 |
15% |
0 |
5.00% |
2.00% |
13.00% |
5.00% |
0 |
Foopath slab concreting(cast in situ) ,precast slab concreting completed.Inner kerb,approach slab concreting completed last week.Painting works in progress. |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
Painting of all spans completed |
12 |
BEAM/SLAB M.C SIDE |
12 |
11 |
1 |
0 |
1 |
1 |
0 |
0 |
0 |
Painting work of the beam and deck slab bottom are COMPLETED. 12 spans have been completed.PAINTING OF (Piercap and pier) completed for 11 locations.drainage spout work completed in 11 spans |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
100% |
0% |
0 |
8.00% |
3.00% |
0.00% |
8.00% |
0 days |
footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion completed 100%..Precast slab fixing completed 100%.Handrail painting completed in shornur side deck slabs |
14 |
HR/FP/KERB M.C SIDE |
100% |
90 |
10% |
0 |
10.00% |
5.00% |
6.00% |
10.00% |
|
.Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress(100%).Deck slab cleaning in progress.PVC pipe laying completed on one side in 11 spans.DRAINAGE SPOUT work completed in M.C side.PAINTING OF OUTER KERB AND HANDRAILS PLANNED NEXT WEEK. |
15 |
BC/PAINTING |
100% |
60 |
55% |
0 |
20.00% |
15.00% |
0.00% |
20.00% |
|
painting in progress .PAINTING OF DECK SLAB BOTTOM complete for 13 spans.painting of (pier and pier cap) completed for 11locations.RCC Wall,RE wall,Outer kerb,Handrail balance work.Painting work completed at handrail portion at spans P1-P2,AP1-P1, in shornur side.Painting in M.C side in progress at outer kerb and handrails |
16 |
METALLING |
100 |
12 |
78 |
|
|
|
|
|
|
METALLING works -WBM WORKS COMPLETED (ALL LAYERS) COMPLETED IN SHORNUR SIDE AND M.C SIDE. |
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
18 |
RCC WALL M.C SIDE |
100% |
90 |
10 |
|
8.00% |
5.00% |
|
10.00% |
|
.Handrail post concreting completedin RCC wall portion 100%,RCC wall concreting completed 100% on M.C side.outer kerb ,cornice completed 100% on RCC retainiing wall.Backfilling of soil completed upto 100%.Inner kerb PCC completed in M.C side.Inner kerb shuttering in progress |