Prevoius Weekly Reports

   Weekly progress report as on 23.03.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RCC WALL SHORNUR SIDE 100% 92% 8% 0 8.00% 4.00% 63.00% 4.00% 0 APPROACH SLAB CONCRETING completed.Metalling works COMPLETED .Precast slabs concreting completed .Painting works in progress.Inner kerb concreting completed this week .Mastic asphalt work completed this week in shornur side
10 RE/R WALL M.C SIDE 100% 95 15% 0 5.00% 2.00% 13.00% 5.00% 0 Foopath slab concreting(cast in situ) ,precast slab concreting completed.Inner kerb,approach slab concreting completed last week.Painting works  in progress.
11 BEAM/SLAB SHORNUR SIDE 3 2 1 0 0 0 0 0 0 Painting of all spans completed
12 BEAM/SLAB M.C SIDE 12 11 1 0 1 1 0 0 0 Painting work of the beam and deck slab bottom are COMPLETED. 12 spans have been completed.PAINTING OF (Piercap and pier) completed for 11 locations.drainage spout  work completed in 11 spans
13 HR/FP/KERB SHORNUR  SIDE 100% 100% 0% 0 8.00% 3.00% 0.00% 8.00% 0 days footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion completed 100%..Precast slab fixing completed 100%.Handrail painting completed in shornur side deck slabs
14 HR/FP/KERB M.C SIDE 100% 90 10% 0 10.00% 5.00% 6.00% 10.00%   .Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress(100%).Deck slab cleaning in progress.PVC pipe laying completed on one side in 11 spans.DRAINAGE SPOUT work completed in M.C side.PAINTING OF OUTER KERB AND HANDRAILS PLANNED NEXT WEEK.
15 BC/PAINTING 100% 60 55% 0 20.00% 15.00% 0.00% 20.00%   painting in progress .PAINTING OF DECK SLAB BOTTOM complete for 13 spans.painting of (pier and pier cap) completed for 11locations.RCC Wall,RE wall,Outer kerb,Handrail balance work.Painting work completed at handrail portion at spans P1-P2,AP1-P1, in shornur side.Painting in M.C side in progress at outer kerb and handrails
16 METALLING 100 12 78             METALLING works -WBM WORKS COMPLETED (ALL LAYERS) COMPLETED IN SHORNUR SIDE AND M.C SIDE.
17 Utility shifting                    
18 RCC WALL M.C SIDE 100% 90 10   8.00% 5.00%   10.00%   .Handrail post concreting completedin  RCC wall portion 100%,RCC wall concreting completed 100% on M.C side.outer kerb ,cornice completed 100% on RCC retainiing wall.Backfilling of soil completed upto 100%.Inner kerb PCC completed in M.C side.Inner kerb shuttering in progress 

 

 