Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051765
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress as on 23.03.12
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 6 0 0 0 0 0 0    
4 PILE CAP  NADAPURAM SIDE 9 9 0 0 0 0 0 0    
  PIER KAINATTY  SIDE 6 6 0 0 0 0 0 0    
6 PIER NADAPURAM SIDE 9 9 0 0 0 0 0 0    
7 PIER CAP KAINATTY  SIDE 6 6 0 0 0 0 0 0    
8 PIER CAP NADAPURAM SIDE 9 9 0 0 0 0 0 0    
11 RE/R WALL KAINATTY  SIDE 100% 99% 1% 1% 3.00% 2.00% 1.00% 1.00%   Painting left.
10 RE/R WALL NADAPURAM SIDE 100% 99% 1% 1% 5.00% 2.00% 1.00% 1.00%   Painting left.
12 BEAM/SLAB  Staging Kainatty side 6 5 1 1 1 1 1 0    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 5 1 1 1 1 1 0    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 5 1 1 1 0 1 1    
15 BEAM/SLAB  Staging Nadapuram side 9 8 1 1 0 0 1 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 8 1 1 1 1 1 1   P6-P7 girder completed.
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 8 1 1 1 0* 1 1   P6-P7 girder completed.
18 BEAM/SLAB KAINATTY  SIDE 6 5 1 1 1 1 1 0    
19 BEAM/SLAB NADAPURAM SIDE 9 8 1 1 1 1 2 1   Steel work for P6-P7 slab in progress.
20 HR/FP/KERB KAINATTY  SIDE 100% 100% 0% 0% 50.00% 50.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 100% 0% 0% 10.00% 10.00% 0.00% 0.00%    
22 BC/PAINTING 100% 40% 60% 60% 10.00% 10.00% 60.00% 20.00%    
                       
                       
  Note: Progress review done based on the revised Program (rev-01)          
                       
                       
  Availbility of Men                     
  Date   17-03-12 18-03-12 19-03-12 20-03-12 21-03-12 22-03-12 23-03-12    
  Nof labours   15 15 20 20 20 20 20    
                       
  Material Stocking Status Required Available Remarks              
                       
  Fine Aggreagate(m3) 3 3                
  Cement(bag) 10 425                
  Steel(MT) 0.5 0.5                
  Coarse Aggreagate (m3) 2 6                
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL in progress                  
  KSEB shifted                  
  KWA shifted                  
  Others shifted                  
 
Back
 
    
WBM WORK AT KAINATTY SIDE.

    
    
MASTIC AT KAINATTY SIDE

    
    
MASTIC APPLICATION AT NADAPURAM SIDE

    
    
HOT MIX PLANT

    
 
    
DRINAGE WORK AT KAINATTY SID

      
 

 

 

 

 

 

 

 

Untitled Document