Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888627
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   15-6-2010
    

ROB at Koratty

PROGRESS AS ON 12-6-2010

 

Work Planned upto 12/6/2010

Completed / Progress

Remarks

P3-P4 Span   Road Blocked for P3-P4 span work.
Preparation for final stressing In progress  
Concreting of Slab Completed  
Approval of GAD by railways (Railway Portion) Approved Approved on 1-5-10
Preparation of Design and Drawing In progress  
Box culvert works (under pass) - Raft concreting Completed  
Wall concreting In progress  
 