   Weekly progress report as on 23.03.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 0 - - - - -
3 Pier  21 16 5 3 5 2 3 3
4 PierCap 21 7 14 - 2 2 - 2
5 Deck Slab 21 0 21 1 1 - 1 1
                   
Date 17.03.12 19.03.12 20.03.12 21.03.12 22.03.12 23.03.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 38 38 38 38 46 46      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 50 m3 20m3              
Coarse Aggregate 100 m3 20 m3              
Cement 747 bags 150 Bags              
Steel 15 MT 20 MT              
                   
 