   weekly progress 23.3.2012
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 22.03.12
Si No  Activity Description  Total Quantity Cumulative progress upto 22.03.12 Balance  work up to 22.03.12 Cumulative delay in Qty up to 22.03.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0
2 PILE Palarivattom side(railway portion) 6 1 5 0 1 1 0 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0
4 PILE vytilla side(railway portion) 6 4 2 0 2 2 0 2
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 0 0 0 0
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 8 1 0 1 1 0 1
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
9 PIER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
11 PIER Vytilla side(Approach portion) 9 6 3 0 2 0 2 2
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0
14 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0
15 DECK SLAB Palarivattom side(Approach portion) 7 5 2 0 1 1 0 0
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
17 PIER CAP  Vytilla side(Approach portion) 9 4 5 0 0 0 0 1
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
19 RE WALL PANEL 351 351 0 0 0 0 0 0
20 RE WALL PCC Palarivattom 95 45 50 0 0 0 0
 
Back
 
    
PUMP SETTING AT P7

    
    
PIER P5 CONCRETING

    
    
GIRDER LIFTING P11P12.

    
    
CAGE LOWERING RP1 P2

    
 
    
BORING RP1 P1

    
    
RE WALL PLRVTM SIDE

      
 

 

 

 

 

 

 

 