   Weekly progress report as on 16.03.12
    
Sl No  Activity Description  Total Quantity Cumulative progress upto 16.3.12 Balance  work up to 16.3.12 Cumulative delay in Qty up to 16.3.12 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4   4          
9 GIRDER Anayara side(Approach portion) 4   4          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 88 12          
13 RT Wall Anayara side(Approach portion) % 100 65 35          
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 225 175     123    
 