   Weekly progress report as on 16/03/12
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 18 3 - 2 3 - -
3 Pier  21 13 8 - 2 3 - 5
4 PierCap 21 7 14 2 2 - 2 2
5 Deck Slab 21 0 21 1 - - 1 1
                   
Date 10.03.12 12.03.12 13.03.12 14.03.12 15.03.12 16.03.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 38 38 38 38 38 38      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 50 m3 20m3              
Coarse Aggregate 100 m3 20 m3              
Cement 870 bags 150 Bags              
Steel 15 MT 20 MT              
 
Back
 
    
PILE CAP P2

    
    
PIER P4

    
    
PIER CAP P13

    
    
P18-P19 STAGING

    
 
    
GIRDER P17-P18

      
 

 

 

 

 

 

 

 