Prevoius Weekly Reports

   weekly progress 16.3.2012
    

 

SlNo

Total Qunatity

Cumulative progress

Balance Quantity

Approach spans at Pulikkakadavu side

6

6

0

Railway span

3

0

3

Re wall at Nh side

100

50

50

RE wall at Puliakkakadavu side

100

100

0

Road work at Pulikakkadavu side

100

100

0

 

 

 

 

Works under Caution -Railway Portion

 

 

SlNo

Total Qunatity

Cumulative progress

Balance Quantity

Pile

10

10

0

Pile cap

2

2

0

Pier

2

2

0

Pier cap

2

1

1

Deck slab

3

0

 
 
Back
 
    
CURING WORK IN PROGRESS AT TRESTLE BEAM AT P7

    
    
FOUNDATION WORKS IN PROGRESS FOR STAGING WORK AT P2-P8

    
    
CURING WORK IN PROGRESS AT TRESTLE BEAM AT P7

    
    
TRESTLE BEAM READY FOR CONCRETE AT P7.

    
 
 
 

 

 

 

 

 

 

 