   Weekly progress report as on 09.03.2012
    
 

Sl No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE CHERUVATHOOR  SIDE

27

27

Completed

 

 

 

 

 

 

2

PILE PADANNA SIDE

24

24

Completed

 

 

 

 

 

Piling works completed.

3

PILE CAP CHERUVATHOOR SIDE

9

9

Completed

 

 

 

 

 

 

4

PILE CAP  PADANNA SIDE

8

7

1

0

1

0

1

1

 

5

PIER CHERUVATHOOR SIDE

9

9

Completed

 

 

 

 

 

P10,P9,P8 Piers complete

6

PIER PADANNA SIDE

8

7

1

0

1

0

0

1

 

7

PIER CAP CHERUVATHOOR SIDE

9

6

3

1

1

0

1

0

 

8

PIER CAP PADANNA SIDE

8

6

2

0

1

0

1

1

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

10%

90%

10%

10.00%

10.00%

0.00%

10.00%

RE panel 200 nos casting complete,Retaining wall first lift complete at LHS

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

4

5

0

0

0

0

0

 

12

BEAM/SLAB PADANNA SIDE

8

2

6

2

2

0

2

2

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

  

 

 
Back
 
    
VIEW OF PADANNA SIDE

    
    
STAGING FOR P7 PIER CAP IP

    
    
RE PANEL EXCAVATION IP

    
    
P10 PIER CAP

    
 
    
P3-P4 SHUTTERING IP

    
    
BM DONE NEAR AP1 TO RLWY STN ROAD

      
 

 

 

 

 

 

 

 