Prevoius Weekly Reports

   Weekly progress report as on 09.03.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

9

RCC WALL SHORNUR SIDE

100%

90

15%

0

10.00%

5.00%

63.00%

10.00%

0

10

RE/R WALL M.C SIDE

100%

90

15%

0

10.00%

5.00%

13.00%

10.00%

0

11

BEAM/SLAB SHORNUR SIDE

3

2

1

0

0

0

0

0

0

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

13

HR/FP/KERB SHORNUR  SIDE

100%

80

20%

0

8.00%

3.00%

0.00%

8.00%

0 days

14

HR/FP/KERB M.C SIDE

100%

90

10%

0

10.00%

5.00%

6.00%

10.00%

 

15

BC/PAINTING

100%

45

55%

0

20.00%

15.00%

0.00%

20.00%

 

16

METALLING

100

12

78

 

 

 

 

 

 

17

Utility shifting

 

 

 

 

 

 

 

 

 

18

RCC WALL M.C SIDE

100%

85

20

 

8.00%

5.00%

 

8.00%

 

 
Back
 
    

    
    

    
    

    
    

    
 
    

    
    

      
 

 

 

 

 

 

 

 