   Weekly progress report as on 09.03.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 17 4 1 2 1 1 2
3 Pier  19 12 7 1 2 1 1 2
4 Pier-Abutment 2 1 1 1 1 - 1 1
5 PierCap 19 6 13 2 2 - 2 2
  Pier Cap -Abutment 2 1 1 - - 1 - -
6 Deck Slab 19 0 19 - 1 - 1 -
                   
Date 02.03.12 03.03.12 05.03.12 06.03.12 07.03.12 08.03.12 09.03.12    
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant    
No. of labours 38 38 38 38 38 38 38    
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 10m3              
Coarse Aggregate 40 m3 20 m3              
Cement 298 bags 160 Bags              
Steel 5 MT 30 MT              
                   
                   
 
Back
 
    
PILE CAP - AP1 -1

    
    
PIER CAP P12

    
    
P17-P18 GIRDER REINFORCEMENT

      
 

 

 

 

 

 

 

 