   weekly progress 9.3.2012
    

 

 

 

SlNo Total Qunatity Cumulative progress Balance Quantity
Approach spans at Pulikkakadavu side 6 6 0
Railway span 3 0 3
Re wall at Nh side 100 50 50
RE wall at Puliakkakadavu side 100 100 0
Road work at Pulikakkadavu side 100 100 0
       
Works under Caution -Railway Portion    
SlNo Total Qunatity Cumulative progress Balance Quantity
Pile 10 10 0
Pile cap 2 2 0
Pier 2 2 0
Pier cap 2 1 1
Deck slab 3 0 3
 
Back
 
    
SHUTTERING AND SUPPORTING WORK FOR TRESTLE BEAM AT P7

    
    
CURING WORK FOR TRESTLE COLUMN 2ND LIFT AT P7.

      
 

 

 

 

 

 

 

 