Prevoius Weekly Reports

   weekly progress as on 9.3.2012
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 09.03.12
Si No  Activity Description  Total Quantity Cumulative progress upto 09.03.12 Balance  work up to 09.03.12 Cumulative delay in Qty up to 09.03.12 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week 
1 PILE  Palarivattom side(Approach portion) 31 29 2 0 2 1 1 2
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0
4 PILE vytilla side(railway portion) 6 1 5 0 0 0 0 1
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 0 0 0 0
6 PILE CAP Palarivattom side(railway portion) 1 1 0 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 6 3 0 1 1 0 1
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
9 PIER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
11 PIER Vytilla side(Approach portion) 9 4 5 0 2 0 2 2
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0
14 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0
15 DECK SLAB Palarivattom side(Approach portion) 7 5 2 0 1 1 0 0
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
17 PIER CAP  Vytilla side(Approach portion) 9 2 7 0 0 0 0 1
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
19 RE WALL PANEL 351 351 0 0 0 0 0 0
20 RE WALL PCC Palarivattom 95 45 50 0 0 0 0 0
 
Back
 
    
SLUMP CHECKINGP9 P4.

    
    
DECK REINFORCEMENT P11P10.

    
    
LINER DRIVING RP2 P4.

    
    
PILE CONCRETING RP1 P6

    
 
    
RE WALL PCC PALARIVATTOM SIDE.

      
 

 

 

 

 

 

 

 