Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886925
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 9.3.2012
    

 

Progress Report For ROB Puliyanam for the week ending on 09/03/2012
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Puliyanamside 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 100% 0% 0 0% 0% 0% 0% TARGET ACHIEVED
6 RC wall at NH side 100% 80% 20% 0 0% 0% 0% 0%  
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 54 48 0 0 0 0 0 0 TARGET ACHIEVED
12 Beam and cross beam at NH side 6 3 3 0 0 0 0 0  
13 Beam and cross beam at Puliyanam side  4 1 4 0 1 0 1 0  
14 Deck slab  at NH side  6 3 3 0 0 0 0 0  
15 Deck slab  at Puliyanam side  4 1 3 0 0 0 0 0  
16 Dirt wall  2 2 0 0 0 0 0 0 TARGET ACHIEVED
17 Kerb NH side 100% 35% 65% 0 0 0 0 0  
18 Kerb Puliyanam side 100% 15% 85% 0 0 0 0 0  
19 Earth filling in approach embankment  100% 50% 50% 0 0 0 0 0  
                     
Date 03.03.12 05.03.12 06.03.12 07.03.12 08.03.12 09.03.12        
Climate pleasant pleasant pleasant pleasant pleasant pleasant        
No.of labours 50 51 53 52 54 51        
                     
availability of material                    
materials Required Available                
Fine aggregate(M3) 30 37                
Coarse aggregate(M3) 40 50                
Cement(BAG) 700 450                
Steel(TONN) 21 45                
 
Back
 
    
RC WALL EXCAVATION NH SIDE ,05.03.2012

    
    
P6-P7 BEAM REINFORCEMENT WORK,06.03.2012

    
    
ROAD DIVERSION NH SIDE ,03.03.2012

    
    
P1-P2 BEAM SHUTTERING ,07.03.2012

    
 
    
P2-P3 STAGING ,08.03.2012

      
 

 

 

 

 

 

 

 

Untitled Document