Progress Report For ROB Puliyanam for the week ending on 09/03/2012 |
Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
Pile towards NH side |
26 |
26 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
2 |
Pile towards Puliyanam side |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
3 |
Pile cap at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
4 |
Pile Cap at Puliyanamside |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
5 |
RC wall at Puliyanam side |
100% |
100% |
0% |
0 |
0% |
0% |
0% |
0% |
TARGET ACHIEVED |
6 |
RC wall at NH side |
100% |
80% |
20% |
0 |
0% |
0% |
0% |
0% |
|
7 |
Pier at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
8 |
Pier at Puliyanam Side |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
9 |
Piercap at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
10 |
Piercap at Puliyanam |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
11 |
PEDESTAL |
54 |
48 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
12 |
Beam and cross beam at NH side |
6 |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
|
13 |
Beam and cross beam at Puliyanam side |
4 |
1 |
4 |
0 |
1 |
0 |
1 |
0 |
|
14 |
Deck slab at NH side |
6 |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
|
15 |
Deck slab at Puliyanam side |
4 |
1 |
3 |
0 |
0 |
0 |
0 |
0 |
|
16 |
Dirt wall |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
17 |
Kerb NH side |
100% |
35% |
65% |
0 |
0 |
0 |
0 |
0 |
|
18 |
Kerb Puliyanam side |
100% |
15% |
85% |
0 |
0 |
0 |
0 |
0 |
|
19 |
Earth filling in approach embankment |
100% |
50% |
50% |
0 |
0 |
0 |
0 |
0 |
|
|
|
|
|
|
|
|
|
|
|
|
Date |
03.03.12 |
05.03.12 |
06.03.12 |
07.03.12 |
08.03.12 |
09.03.12 |
|
|
|
|
Climate |
pleasant |
pleasant |
pleasant |
pleasant |
pleasant |
pleasant |
|
|
|
|
No.of labours |
50 |
51 |
53 |
52 |
54 |
51 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
availability of material |
|
|
|
|
|
|
|
|
|
|
materials |
Required |
Available |
|
|
|
|
|
|
|
|
Fine aggregate(M3) |
30 |
37 |
|
|
|
|
|
|
|
|
Coarse aggregate(M3) |
40 |
50 |
|
|
|
|
|
|
|
|
Cement(BAG) |
700 |
450 |
|
|
|
|
|
|
|
|
Steel(TONN) |
21 |
45 |
|
|
|
|
|
|
|
|