Kundannur Flyover
Project Graph
|
Photo Album
![](sites/all/themes/rbdck2013/images/butn.png) |
Weekly Progress Report - 07.12.2020 to 12.12.2020 |
|
Weekly Progress Report - 07.12.2020 to 12.12.2020 |
07.12.2020 |
08.12.2020 |
09.12.2020 |
10.12.2020 |
11.12.2020 |
12.12.2020 |
Strip filling at expansion joint work will starts.
|
Site levelling work LHS Aroo |
Site clearing work starts for drain at LHS (Infront of KNA Plaza.
|
Road Marking |
Site clearing work starts for drain at Thripunitura road drain. |
Site clearing work starts for drain at Thripunitura road drain.
|
Deshuttering work at RHS drain (Infront of Airtel building). Drain slab laying will starts at Slip road drain.
|
Kerb laying LHS Aroor |
Drain slab laying will starts at Pamba steel area drain. |
|
Road marking starts at LHS. |
Road marking starts at LHS. |
Planning for PCC at A1-P0 span. |
Cover slab laying for drain
|
Painting work progressing at bridge portions. |
|
Painting work progressing at electric pole. |
Painting work progressing at electric pole.
|
Painting work progressing at bridge portions. |
Painting work |
|
|
|
|
|
|
|
|
|
|
|
|
|
Click here to view Previous Reports |
|
ROAD MARKING
|
| | |
PAINTING
|
| | |
ROAD MARKING
|
| | |
PAINTING
|
| | |
DRAINAGE WORK
|
| | |
ROAD MARKING
|
| | |
KERB PAINTING
|
| | |
DRAINAGE WORK
|
| | |
|
| | |
|
| | |
|
| | |
|
| | |
PAINTING
|
| | |
SHUTTERING WORK
|
| | |
PAINTING
|
| | |
PCC WORK
|
| | |
|
|