Prevoius Weekly Reports

   Weekly progress report as on 2.03.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 15 6 - 2 2 - 2
3 Pier  19 10 9 - 2 2 - 2
4 Pier-Abutment 2 1 1 - 1 1 - 1
5 PierCap 19 6 13 - 2 - 2 2
  Pier Cap -Abutment 2 - 2 - 1 1 - -
6 Deck Slab 19 0 19 - - - - 1
                   
Date 25.02.12 27.02.12 28.02.12 29.02.12 01.03.12        
Climate Pleasant Pleasant Pleasant Pleasant Pleasant        
No. of labours 28 28 28 28 28        
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 55 m3 15m3              
Coarse Aggregate 110 m3 20 m3              
Cement 956 bags 480 Bags              
Steel 15 MT 20 MT              
                   
 
Back
 
    
PILE CAP P4

    
    
PIER P8

    
    
PIER CAP AP2

    
    
DECK SLAB STAGING P17-P18

    
 
 
 

 

 

 

 

 

 

 