   Weekly progress report as on 2.03.2012
    
Progress Report For Devdhar ROB for the week ending on 02-03-2012  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0    
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0    
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0    
4 PILE CAP  THIRURSIDE 6 6 0 5 1 1 5 0    
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0    
6 PIER THIRUR SIDE 6 5 1 1 1 1 1 0    
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0    
8 PIER CAP THIRUR SIDE 6 4 0 3 2 2 3 0    
9 RE/R WALL CALICUT   SIDE 100% 5.00% 95% 0 2.00% 0.00% 2.00% 5.00%    
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM CALICUT   SIDE 12 1 11 0 1 1 2 1   P6-P7 in progress
12 SLAB CALICUT SIDE                    
13 BEAM THIRUR SIDE 6 0 6 0 0 0 0 0    
14 SLAB TIRUR SIDE                    
15 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                   
  Date 25-02-2012 26-02-2012 27-02-2012 28-02-2012 29-02-2012 01-02-2012 02-02-2012      
  Nof labours 34 34 34 0 34 34 34      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 28 21                
  Fine Aggreagate(m3) 18 10                
  Cement(bag) 450 190                
  Steel(MT)   16                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL shifting completed                  
  KSEB shifting in progress                  
  KWA shifting completed                  
  Others                    
                       
                       
 