Prevoius Weekly Reports

   Weekly progress report as on 24.02.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RCC WALL SHORNUR SIDE 100% 82 18% 0 15.00% 3.00% 63.00% 8.00% 0 APPROACH SLAB CONCRETING completed.Metalling works to be commenced today.
10 RE/R WALL M.C SIDE 100% 78 22% 0 20.00% 3.00% 13.00% 10.00% 0 Friction slab concreting completed for a distance of 35 METRES on both sides.Outer kerb concreting completed for a distance of 35 metres on both sides..APPROACH SLAB CONCRETING completed.INNER KERB concreting complete for a distance of 25 metres on one side.Handrail fixing to be commenced soon.
11 BEAM/SLAB SHORNUR SIDE 3 2 1 0 0 0 0 0 0 Painting of two spans completed .AP1,P1
12 BEAM/SLAB M.C SIDE 12 11 1 0 1 1 0 0 0 Painting work of the beam and deck slab bottom are COMPLETED.ELEVEN   spans have been completed.PAINTING OF (Piercap and pier) completed for 3 locations.Drilling for drainage spout  in progress.rainage spout work complete in 5 spans.
13 HR/FP/KERB SHORNUR  SIDE 100% 75 25% 0 8.00% 0.00% 0.00% 8.00% 0 days footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion completed 100%.
14 HR/FP/KERB M.C SIDE 100% 80 21% 0 10.00% 2.00% 6.00% 10.00%   .Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress.Deck slab cleaning in progress.PVC pipe laying completed on one side in 11 spans.DRAINAGE SPOUT drilling in progress  in M.C side.
15 BC/PAINTING 100% 45 55% 0 20.00% 15.00% 0.00% 20.00%   painting in progress .PAINTING OF DECK SLAB BOTTOM complete for 13 spans.painting of (pier and pier cap) completed for 3 locations. 

 

Availbility of Men               
Date 18-2-2012 19-2-212 20-2-2012 21-2-2012 22-2-2012 23-2-2012 24-2-2012
Nof labours 40 41 40 40 41 41 40 

 

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 300 356      
Cement(bag) 300 120 stock will be replendished    
Steel inT 5.5 5.25 stock will be replendished    
Coarse Aggreagate (cft) 300 400      

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 
 
Back
 
    
RCC RETAINING WALL CONCRETING COMPLETE ON M.C SIDE.ON 18-2-2012

    
    
PAINTING OF P3,P4,P5 COMPLETE INCLUDING PIER AND PIER CAP(22-2-2012)

    
    
FOOTPATH SLAB CONCRETING IN P5-P6 SPAN IN M.C SIDE(22-2-2012)

    
    
CONCRETING OF RCC RETAINING WALL 1ST LFT COMPLETED TILL THE END ON M.C SIDE (18-2-2012)

    
 
    
CONCRETING OF OUTER KERB AND CORNICE AT RCC WALL PORTION(23-2-2012)

      
 

 

 

 

 

 

 

 