Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
|
|
|
Completed |
|
|
|
2 |
PILE M.C SIDE |
36 |
36 |
|
|
|
Completed |
|
|
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
6 |
PIER M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
9 |
RCC WALL SHORNUR SIDE |
100% |
82 |
18% |
0 |
15.00% |
3.00% |
63.00% |
8.00% |
0 |
APPROACH SLAB CONCRETING completed.Metalling works to be commenced today. |
10 |
RE/R WALL M.C SIDE |
100% |
78 |
22% |
0 |
20.00% |
3.00% |
13.00% |
10.00% |
0 |
Friction slab concreting completed for a distance of 35 METRES on both sides.Outer kerb concreting completed for a distance of 35 metres on both sides..APPROACH SLAB CONCRETING completed.INNER KERB concreting complete for a distance of 25 metres on one side.Handrail fixing to be commenced soon. |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
Painting of two spans completed .AP1,P1 |
12 |
BEAM/SLAB M.C SIDE |
12 |
11 |
1 |
0 |
1 |
1 |
0 |
0 |
0 |
Painting work of the beam and deck slab bottom are COMPLETED.ELEVEN spans have been completed.PAINTING OF (Piercap and pier) completed for 3 locations.Drilling for drainage spout in progress.rainage spout work complete in 5 spans. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
75 |
25% |
0 |
8.00% |
0.00% |
0.00% |
8.00% |
0 days |
footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion completed 100%. |
14 |
HR/FP/KERB M.C SIDE |
100% |
80 |
21% |
0 |
10.00% |
2.00% |
6.00% |
10.00% |
|
.Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress.Deck slab cleaning in progress.PVC pipe laying completed on one side in 11 spans.DRAINAGE SPOUT drilling in progress in M.C side. |
15 |
BC/PAINTING |
100% |
45 |
55% |
0 |
20.00% |
15.00% |
0.00% |
20.00% |
|
painting in progress .PAINTING OF DECK SLAB BOTTOM complete for 13 spans.painting of (pier and pier cap) completed for 3 locations. |