Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8054168
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 24.02.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 22 2 2 2 1 1 1    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 7 1 0 0 0 0 0    
5 PIER CHERUVATHOOR SIDE 9 6 3 1 2 0 2 2   P10,P9,P8 Piers first lift complete
6 PIER PADANNA SIDE 8 7 1 0 0 0 0 0    
7 PIER CAP CHERUVATHOOR SIDE 9 5 4 1 0 0 1 0    
8 PIER CAP PADANNA SIDE 8 6 2 0 1 0 1 1    
9 RE/R WALL CHERUVATHOOR  SIDE 100% 0 100% 0 10.00% 10.00% 0.00% 10.00%   RE panel 135 nos casting complete,Retaining wall raft complete for 25m
10 RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 4 5 0 0 0 0 0    
12 BEAM/SLAB PADANNA SIDE 8 1 7 1 1.5 1 0.5 0.5   P1-P2 deck slab complete
13 HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men               
Date 18-02-2012 19-02-2012 20-02-2012 21-02-2012 22-02-2012 23-02-2012 24-02-2012
No of labours 76 45 76 76 63 68 70 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available
Fine Aggreagate(m3) available
Cement(bag) 800 1200
Steel(MT) 12 20 

 

Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1 locationclearedfor piling,P10 shifting complete,cables at approach portion to be shifted
KSEB in progress estimation received.work to be started urgently.
KWA currently can be managed at site        

 

 
Back
 
    
STAGING FOR P5-P6 IP

    
    
RC WALL RAFT WORKS IP AT CHR SIDE

    
    
PILING IP AT AP1

    
    
EXCAVATION IP FOR RE PANEL

    
 
    
BUILDING DEMOLITION IP AT PADANNA SIDE

      
 

 

 

 

 

 

 

 

Untitled Document