Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
22 |
2 |
2 |
2 |
1 |
1 |
1 |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
6 |
3 |
1 |
2 |
0 |
2 |
2 |
|
P10,P9,P8 Piers first lift complete |
6 |
PIER PADANNA SIDE |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
5 |
4 |
1 |
0 |
0 |
1 |
0 |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
6 |
2 |
0 |
1 |
0 |
1 |
1 |
|
|
9 |
RE/R WALL CHERUVATHOOR SIDE |
100% |
0 |
100% |
0 |
10.00% |
10.00% |
0.00% |
10.00% |
|
RE panel 135 nos casting complete,Retaining wall raft complete for 25m |
10 |
RE/R WALL PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
4 |
5 |
0 |
0 |
0 |
0 |
0 |
|
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
1 |
7 |
1 |
1.5 |
1 |
0.5 |
0.5 |
|
P1-P2 deck slab complete |
13 |
HR/FP/KERB CHERUVATHOOR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
14 |
HR/FP/KERB PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|