Prevoius Weekly Reports
|
06.07.2010 |
|
ROB at Bakel
Work Planned upto 06/07/2010 |
Completed / Progress |
Span of Kasargod side |
|
Concreting Beam and Slab |
Completed |
Hand Rail & Foot Path Casting |
In progress |
Outer Kerb casting |
In progress |
|
|
Back |
|
No images are uploaded for this Weekly Reports
|
|
|