Prevoius Weekly Reports

   Weekly progress report as on 24.02.2012
    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side completed Done LHS 100%, RHS- 100%
  Retaining wallcalicut side In progress 60% completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Handrail fixing In progress NH side 10 slab completed.
  Handrail fixing In progress CALICUT side 8 span over.
  Boring at RP4 & RP1 Completed PILING COMPLETED
  Boring at RP3 In progress 4-PILE CONCRETED
  Boring at RP2 In progress RP2-3  pile concreted.
  NH side RE panel erection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab In progress 80% completed.
 
Back
 
    
RP1 AFTER PILE CHIPPING.

    
    
PAINTING

    
    
EARTH FILLING RP2.

    
    
CAPPING BEAM WORK.

    
 
    
BORING RP3-3

    
    
AP2 SIDE BRIDGE.

      
 

 

 

 

 

 

 

 