   Weekly progress Report as on 24.02.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks   
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0      
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0      
3 PILE CAP KAINATTY SIDE 6 6 0 0 0 0 0 0      
4 PILE CAP  NADAPURAM SIDE 9 9 0 0 0 0 0 0      
  PIER KAINATTY  SIDE 6 6 0 0 0 0 0 0      
6 PIER NADAPURAM SIDE 9 9 0 0 0 0 0 0      
7 PIER CAP KAINATTY  SIDE 6 6 0 0 0 0 0 0      
8 PIER CAP NADAPURAM SIDE 9 9 0 0 0 0 0 0      
11 RE/R WALL KAINATTY  SIDE 100% 97% 3% 3% 15.00% 10.00% 5.00% 3.00%   Friction slab.  
10 RE/R WALL NADAPURAM SIDE 100% 97% 3% 3% 15.00% 10.00% 5.00% 3.00%   Friction slab.  
12 BEAM/SLAB  Staging Kainatty side 6 5 1 1 1 1 1 0      
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 5 1 1 1 1 1 0      
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 5 1 1 1 0 1 1      
15 BEAM/SLAB  Staging Nadapuram side 9 8 1 1 0 0 1 0      
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 8 1 1 1 1 1 1   P6-P7 girder completed.  
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 8 1 1 1 0* 1 1   P6-P7 girder completed.  
18 BEAM/SLAB KAINATTY  SIDE 6 5 1 1 1 1 1 0      
19 BEAM/SLAB NADAPURAM SIDE 9 8 1 1 1 1 2 1   Steel work for P6-P7 slab in progress.  
20 HR/FP/KERB KAINATTY  SIDE 100% 99% 1% 1% 50.00% 49.00% 1.00% 1.00%      
21 HR/FP/KERB NADAPURAM SIDE 100% 99% 1% 1% 10.00% 10.00% 1.00% 1.00%      
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
                         
                         
  Note: Progress review done based on the revised Program (rev-01)            
                         
                         
  Availbility of Men                       
  Date   18-02-12 19-02-12 20-02-12 21-02-12 22-02-12 23-02-12 24-02-12      
  Nof labours   29 29 29 24 24 24 24      
                         
  Material Stocking Status Required Available Remarks                
                         
  Fine Aggreagate(m3) 10 6                  
  Cement(bag) 150 750                  
  Steel(MT) 3 5                  
  Coarse Aggreagate (m3) 12 6                  
                         
  Utility shifting                      
  Utilities to be shifted Status Remarks                  
  BSNL in progress                    
  KSEB shifted                    
  KWA shifted                    
  Others shifted                    
 
Back
 
    
KERB ABOVE RCC WALL AT NADAPURAM SIDE

    
    
FRICTION SLAB-KAINATTY SIDE

    
    
DECK SLAB CLEANING FOR MASTIC

    
    
CHIPPING OFF EXTRA CONCRETE

    
 
 
 

 

 

 

 

 

 

 