Revised Progress Report For Ponnurunni ROB for the week ending on 23.02.12
Si No  Activity Description  Total Quantity Cumulative progress upto 23.02.12 Balance  work up to 23.02.12 Cumulative delay in Qty up to 23.02.12 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 4 3 1 3
4 PILE vytilla side(railway portion) 6 1 5 0 0 0 0 0
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0
6 PILE CAP Palarivattom side(railway portion) 1 1 0 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 4 5 0 2 0 2 2
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
9 PIER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
11 PIER Vytilla side(Approach portion) 9 2 7 0 2 0 2 2
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 2 2
14 GIRDER Palarivattom side(Approach portion) 7 6 1 0 1 1 0 0
15 DECK SLAB Palarivattom side(Approach portion) 7 4 3 0 1 0 1 0
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
17 PIER CAP  Vytilla side(Approach portion) 9 1 8 0 1 1 0 1
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
19 RE WALL PANEL 355 355 0 0 0 1 0
 