ROB at Koratty
|
PROGRESS AS ON 07.11.2009 |
The details are of the work done between 2nd and 7th of November.
|
Work Planned |
Completed/Progress |
Delay |
|
P4 pier cap connecting |
Completed |
1 week due to perunnal |
|
Reinforcement work for I Girder |
In progress |
|
|
Approval of GAD by railways to follow up by contractor |
|
|
|
Re wall in Koratty side |
In progress |
|
|