Sl No
|
Activity Description
|
Total Quantity
|
Cumulative progress upto last week
|
Balance work up to last week
|
Cumulative delay in Qty up to last week
|
Work planned during the week
|
Actual work done during the week
|
Cumulative delay in Qty up to this week
|
Work Planned for next week
|
No of days remaing for completion as per the weekly plan
|
Remarks
|
9
|
RE/R WALL CHERUVATHOOR SIDE
|
100%
|
0
|
100%
|
0
|
0.00%
|
0.00%
|
0.00%
|
0.00%
|
|
RE panel 120 nos casting complete,Retaining wall excavation started,PCC complete for 15 m
|