   Weekly progress report as on 17.02.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 57 6   4 4 - 2
2 Pile cap 21 12 9 - 3 - 3 3
3 Pier  19 9 10 - 2 2 - 2
4 PierCap 19 5 14 1 2 1 1 2
                   
Date 11.02.12 13.02.12 14.02.12 15.02.12 16.02.12 17.02.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 50 50 50 50 50 50      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 40 m3 15m3              
Coarse Aggregate 75 m3 25 m3              
Cement 600 bags 700 Bags              
Steel 5 MT 20 MT              
                   
                   
                   
 