ROB at Koratty
Details of work between 9th to 14th November 2009.
PROGRESS AS ON 07-11-2009 |
Work Planned upto 14/11/2009 |
Completed/Progress |
Delay |
P4 pier cap pedestal |
Completed |
1 week due to Perunnal
(festival)
|
Reinforcement work for I Girder |
In progress |
|
Approval of GAD by railways to follow up by |
|
|
contractor |
|
|
Re wall in Koratty side |
In progress |
|
|